INTRODUCTION

The State of Jammu & Kashmir is striving to meet the growing power demand, and to address legacy issues such as high peak deficit and lack of electricity access to unconnected households. The state government was looking for an alternate power corridor to light up Kashmir. The old transmission corridor that runs from Moga in Punjab and ends just ahead of Jammu at Kishenpur needed to be strengthened and extended further

RELATED CASE STUDIES

Vineyards: Use Of Aerial Technology To Power Brazilian Grid

Skyrob: Making Opgw Stringing Safe

Project Ganga: Excellence In Project Execution And Product Innovation

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60