PROJECT STORY
The Pampa Project has 316 km of transmission line to be built, the implementation of 1 new substation and the expansion of 3 substations in the region to be deployed in the state of Rio Grande do Sul. Power of 1544 MVA.
Project Detail
– LT South 525kV Capivari – Gravataí, C1, with 83 km;
– LT South 230kV Capivari – Viamão 3, C1, with 65 km;
– LT 525kV Guaiba 3 – South Capivari, C1, with 168 km;
– SE 525/230/138 kV South Capivari’s – 525/230 kV – (6 + 1) x 230/138 kV 224 MVA and – 2 x 100 MVA.
TIMELINES
Milestone1 : Preliminary Environmental License
Milestone 2 : Installation Environmental License