Goyaz

Provide greater energy reliability to the state of Goiás.

PROJECT STORY

The Goyaz Project has 154 km of transmission line to be built, and the expansion of 1 other substation in the region of Goiás state. Power of 600MVA.

This project is expected to generate 803 direct / indirect jobs.

Project Detail

Length: 154 km 
Power: 600 MVA    
Deadline: 48 months 
Estimate of direct jobs: 803
State: GO

TIMELINES

Preliminary Environmental license

Installation Environmental license