The Marituba Project has 374 km of transmission line to be built, and the expansion of 2 substations in the region of Pará state.

This project is expected to generate 1245 direct / indirect jobs.

Project Detail

Length: 374 km    
Deadline: 54 months 
Estimate of direct jobs: 1.245
State: PA

TIMELINES

Preliminary Environmental license

Installation Environmental license

PROJECT GALLERY

RELATED LINKS

 MUMBAI URJA MARG LIMITED

GOA TAMNAR TRANSMISSION PROJECT LIMITED

LAKADIA VADODARA TRANSMISSION PROJECT LIMITED (LVTPL)

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60