INTRODUCTION
In 2010, the Brazilian Government’s Energy Planning studies pointed out the need for structural works to follow the growth of the market in the state of Rio Grande do Sul.
In 2010, the Brazilian Government’s Energy Planning studies pointed out the need for structural works to follow the growth of the market in the state of Rio Grande do Sul.
SYSTEM AVAILABILITY |
||
---|---|---|
Projects | DEC 2019 | Availability since COD |
ENICL | 99.82 | 99.54 |
BDTCL | 99.90 | 99.71 |
JTCL | 100.00 | 99.54 |
RTCL | 100.00 | 99.84 |
PKTCL | 100.00 | 99.93 |
NRSS-XXIX | 98.61 | 99.67 |
MTL | 100.00 | 99.95 |
OGPTL | 100.00 | 99.95 |
PTCL | 100.00 | 99.94 |
KTL | 100.00 | 100.00 |
GPTL | 99.81 | 99.60 |